| |
|
|
|
Building Permits and Zoning -
Mike Morgan
Zoning and Permits - all permits are issued at the
Township Hall. Mike Morgan's Email address:
zoningofficial@yahoo.com
|
|
Listed below are
four instruction sheets/check lists outlining the process of zoning, obtaining a building permit,
and other requirements.
They are:
1) ZONING
AND CONSTRUCTION CHECK LIST, 2)
CHECK LIST FOR
OBTAINING A BUILDING PERMIT,
3) REQUIREMENTS FOR OBTAINING BUILDING, PERMITS,
4) CONSTRUCTION AND INSPECTION CHECK LIST,
5) PLAN EXAMINATION - INFORMATION AND INSTRUCTIONS
ZONING AND CONSTRUCTION CHECK LIST
1. Site plan zoning and building permit request
applications must be filled out and returned.
a.
The site plan must include a drawing of any existing
building structures and the location of any new
building or structures including the distance
between the buildings, the building sizes and
setbacks for all sides of the property. It is the
responsibility of the permit applicant to know the
requirements of the Township Zoning Ordinances and
Building Codes. If unsure of these ordinances or
codes, copies are available at the Township Office.
b.
Only one resident per parcel.
2. A driveway permit from the County Road
Commission.
3. A well and septic permit from the County Health
Department.
4. A soil erosion permit if within 500' of a lake,
pond, stream or river from the County Road
Commission.
5. Two copies of the prints or a detailed drawing
showing all four sides with
elevations of the
building or structure; also details on the type of
approved fireproofing to be used between
floors where required.
6. A building permit will be issued when the above
documents have been
submitted and
approved by the Zoning Administrator and the
building inspector; A building permit
application will need to be filled out.
7. The Building Permit must be posted at all times
during construction at road side using a minimum of
3" high letters of
house numbers or name showing location, site.
8. There will be a minimum of three inspections:
footing, rough and final.
9. Footing inspections must be done before they are
back filled.
a. For a house - 42 inches deep.
b. Attached Garage-42 inches deep with continues
footing.
c. Detached
Garage exceeding 400 sg. ft- 4 inches floor with 42
inches deep footing. Unless in #1 soil
condition (sand or gravel) Then it must be a 24 inch
deep Ratwall.
10. Rough inspection will be done after all other
trades' rough are completed.
11.
Final inspections will be done when all other trades
have had their final inspections and all finish work
is done.
12.
Requests for inspection must be made 24 hours in
advance.
|
|
CHECK LIST FOR
OBTAINING A BUILDING PERMIT
Before Clarence Township Can
Issue Your Building Permit, The Following items Need
to Be Furnished to the
Building Permits Officer.
ZONING APPROVAL, this can
be obtained from the zoning official of your township, city or village. This applies to all
structures. Only work done inside of an existing
building is exempt.
SITE PLAN. A site plan must include a drawing of all existing
structures and the location of any new building or
structures including the distance between buildings. the
building dimensions and setbacks for all sides of the
property. Only one residence per parcel.
PLAN AND SPECS,
three (3) sets of plans must be submitted with
application for
plan review procedure. Plans must show the following: Foundation plan,
floor plan, energy code compliance, typical wall section
and exterior elevation drawings. All plans must contain
substantial information concerning: dimensions,
materials, span requirements, and construction methods
used for the submitted project.
PROPERTY ADDRESS,
may be
obtained from your the Calhoun county road
commission.
PROPERTY CODE OR TAX ED. NUMBER
this can be obtained from your tax
bill, your township/city/village offices or Equalization
office at your County
Courthouse.
SEPTIC AND/OR WELL PERMIT,
this can be obtained from your county health
department.
DRIVEWAY
& ADDRESS
PERMIT, this can be obtained from the road
commission.
SOIL EROSION PERMIT,
if applicable. A permit is required for all earth change
activities which disturb ONE (1) or more acres of land OR
if the earth
change is within 500 feet of a
lake, streams, swamp, marsh, pond, county
drain or any
standing water. This can obtained from your County
Public Work Department.
DEPARTMENT OF ENVIRONMENTAL QUALITY,
issues flood plain permit
if the
project is located in part or whole within 100 year regulatory
flood plain of a river, creek, drain or a body of water,
a DNRE permit is
required. ALLOW 4-6 WEEKS FOR PROCESSING,
GOEMAERE-ANDERSON WETLAND PROTECTION ACT,
if your project
is located
in or near wetland contact the DNR. They will
determine
whether or not a parcel of land is under the
jurisdiction of this Wetland-Protection Act,
517-373-3328.
MISS DIG,
must be contacted when any digging is done for the
marking of all underground lines on proposed site,
800-482-7171, building must be thirty five feet (35)
from all overhead power lines.
|
|
REQUIREMENTS FOR OBTAINING BUILDING PERMITS.
Residential Structures
(One-and Two-Family
Residential with less than 3,500 square feet
of
calculated
floor area)
-Building Permit
Application
-Minimum of three
(3) sets of plans that include
the following:
Foundation and floor plans.
Roof and wall section. Building
Elevations.
Site plan.
Commercial
Structures
(Including One-and
Two-Family Residential with more than 3,500 square
feet
of
calculated
floor area)
-Building Permit
Application -Copy of plan review
approval letter. Plan review must be approved prior
to a building permit being issued.
Mobile and
Pre-manufactured Homes
-Building Permit
Application
-Minimum of three (3)
sets of plans for the foundation and the method of
anchoring the unit to the foundation.
-Site plan.
-For Michigan approved
pre-manufactured units; Three (3) copies
of
the Building
System Approval and the approved plans.
Instructions for
Completing Application
Page 1 of the
application: Complete all applicable sections. Note
section Iliac). If the homeowner is doing the
construction,
enter "Homeowner" in the contractor information
space.
Page 2 of the
application: Enter the information as required.
Page 3, Section VI
of
the
application: Must be completed by the permit
applicant and signed.
Section VII.
Must be completed by the local governmental agency
(city/township) for zoning (environmental) approval.
In certain jurisdictions, a land use permit may be
substituted. Note (g) and (h). Indicate whether a
well or septic approval is required. Well and
septic permits are typically issued by the county
health department.
Building Permit Fees
Building permit fees
may be obtained from the Township office.
You will need to
furnish the following information when calling
-Total square footage
of the structure
•:Use
group (i.e., "R-3" use group for single family homes,
"U" use group for detached garages, pole barns,
etc.). Type of construction ("5B" for wood
frame construction).
If you submit your
building permit application and plans without money, your application will be put on hold
and you will receive an invoice for the building
permit fee.
Expiration of Permit
A
permit remains valid as long as work is progressing
and inspections are requested and conducted. A
permit shall become invalid if the authorized work is not
commenced within 180 days after issuance of the
permit or if the authorized
work is
suspended or abandoned for a period of 180 days
after the time of commencing the work. A PERMIT
WILL
BE CLOSED WHEN NO
INSPECTIONS ARE REQUESTED AND CONDUCTED WITHIN 180
DAYS OF THE
DATE OF ISSUANCE
OR THE DATE OF A PREVIOUS INSPECTION. CLOSED PERMITS
CANNOT BE REFUNDED.
THE CHARGE TO RE-OPEN
A CLOSED PERMIT IS
$75.00.
|
|
CONSTRUCTION AND INSPECTION CHECK LIST
Inspection Requirements
Inspections must be called in for, either by the permit
holder or an agent such as the contractor, architect, or
engineer. The permit holder is ultimately responsible
for all construction and inspections. The permit holder
needs to
confirm that all inspections have been called for and
that the inspections have
been completed. A Certificate of Occupancy cannot be issued for any
project which has not been inspected or approved.
There is a minimum of five
(5) inspections:
1) FOOTINGS: Are to be
inspected before they are poured or placed.
2) FOUNDATION/BACKFILL:
Before backfilling
any basement or crawl space. This is to ensure
that proper bracing; drainage and damp proofing have
been completed.
3) ROUGH-IN/FRAMING:
After the building is up, but
before any dry wall or insulation is installed.
4) ENERGY CODE COMPLIANCE
5)
FINAL:
After all work has been completed on the project, but
before occupying the structure. All Electrical,
Mechanical, and Plumbing work
must be completed prior to the final building
inspection.
SECTION R110.1 USE AND OCCUPANCY OF THE MICHIGAN
RESIDENTIAL CODE OF 2009 STATES:
A building or structure shall not be used or occupied,
and a change in the existing occupancy classification of
a building or structure or portion thereof shall not be
made until a certificate of occupancy has been issued
in accordance with the act.
CALL 24 TO 48 HOURS IN ADVANCE FOR ALL INSPECTIONS. THE
INSPECTORS ARE ON YOUR PERMITS.
NOTICE TO HOMEOWNERS:
MCL 3392401 et seq; MSA 18.245
(2401) st seq. (Michigan Public Act 299 of 1980) States
the following:
1. The person or
company who applies and obtains a building permit from
this office ASSUMES SOLE RESPONSIBILITY for the work
that is done pursuant to that permit and is SOLELY
RESPONSIBLE for the compliance with the laws enforced by
this office.
2. The total cost
of labor and materials for any work conducted pursuant
to a building permit issued by this office may not
exceed six hundred dollars (600.00) unless a licensed
residential builder or licensed maintenance alteration
contractor is doing the work. For residential buildings,
the homeowner may do the building him/herself, as long
as this person owns and occupies the home.
3. Please verify
that your builder is licensed. Ask your builder to show
his/her State builders License, and check the expiration
date to be sure that it is not expired. If you have any
doubts, you may contact the Michigan Department of
Licensing, phone number: 517-241-9254
|
|
Clarence Township – Plan
Examination – Information and Instructions
Plan Examination
The purpose of a plan examination is to assure the
construction project is designed in compliance with the
code. If there are issues of noncompliance they may be
addressed during the review process. This saves the
applicant time and money as it is more economical to
make revisions prior to the start of construction.
Who may submit? Construction documents
may be submitted by the owner or the owner's architect,
engineer, contractor, or agent. The construction
statutes or codes do not fix the responsibility for the
submission of construction documents. However, the owner
of the construction project has the responsibility to
assure that it is done.
Is a plan review
necessary? Plans are required for all building
types, except:
Building
-
When repair work is determined by the building
official to be of a minor nature.
-
When utility structures are 100 square feet or less
relative to one-and two-family dwellings.
Electrical
-
When the electrical system rating does not exceed
400 amps and the building is not over 3,500 square
feet in area.
Mechanical
-
One-and two-family dwellings when the total building
heating/cooling system input rating is 375,000 Btu's
or less.
-
Alterations and repair work determined by the
mechanical official to be of a minor nature.
-
Business, mercantile, and storage buildings having
HVAC equipment only, with one fire area and not more
than 3,500 square feet.
-
Work completed by a governmental subdivision or
state agency costing less than $15,000.00.
Plumbing
-
One-and two-family dwellings containing not more
than 3,500 square feet of building area.
-
Alterations and repair work determined by the
plumbing official to be of a minor nature.
-
Assembly, business, mercantile and storage buildings
with a required plumbing fixture count less than 12.
-
Work completed by a governmental subdivision or
state agency costing less than $15,000.00.
Description of Work. The plan examination
submission shall give a complete description of the work
to be performed. This shall include the location, the
occupancy of all parts of the buildings or structures,
and the open space on the lot. Any special inspection
requirements in accordance with section 1705 of the
building code shall be identified.
Site Plan.
The site plan shall provide the location and size of
all buildings on the lot. The roads and access points
and open spaces shall be shown and dimensioned.
Construction Documents. The construction
documents shall indicate the size, shape, and height of
all features of the buildings and structures of the
project. Specific information shall be given to
establish the quality and requirements of the
construction for compliance with the code. The
information may be submitted in any combination of
written and graphic material. The codes shall not be
cited, or the term "legal" or similar shall not be used
in place of specific information. All construction
documents shall be sealed and signed by an architect or
professional engineer licensed in Michigan in accordance
with P.A. 299 of 1980, as amended.
Exception:
·
A residence building not exceeding 3,500 square feet in
calculated floor area.
·
Public work for which the contemplated expenditure for
the completed project is less than $15,000.00.
Engineering Detail.
Structural, mechanical, electrical, and plumbing
work shall include adequate detail including
computation, stress diagrams and other essential
technical data.
How to Submit. Three
(3) sets of construction documents and a completed
Application for Plan Examination must be submitted to
the Plan Review Division. The Fee is determined by the
square footage of the project. When the plan examination
is completed the total charges will be calculated and
any amount due will be billed to the applicant. When the
project is approved and all the fees paid, one set of
approved construction documents will be returned to the
applicant. These documents are to be placed on the
project site and made available for examination by the
code inspectors.
Questions regarding plan
examinations should be directed to the Plan Review
Division |
|
Click to Return to the Top of the page:
Construction Forms
|
|
|